Reassign Tasks Using the Manufacturing Task Scheduler

By looking at the summary bar of a work center, you can check for overlapping tasks, indicating that a work center is overutilized. In this case, you can schedule a work order to a later date, or assign it to another resource.

Reassign a Task

To reassign a task, drag the task bar upward or downward within the same column, toward the new work center. You cannot reassign a task to an inactive work center, or one that belongs to a different subsidiary.

Screenshot of the Manufacturing Task Scheduler page with a task reassignment.

As you drag the task bar, the check icon appears beside the start and end dates. This indicates that you can drop the task onto the specific chart location on the new work center. The reassigned task retains all its details, except for the new work center number.