Scenario:
The deparment field is not available in the project along side of project activity under schedule subtab of project. Here the department field created is linked with the project and the subsidiary, class all are same but its not listed in the project.
Reason :
The Divsion created was linked with the project but inorder to list alongside with the projcet activity, the department must be linked with the activity.
Solution:
Create a new Project activity;
1.Go to project, under schedule click on new activity.
2. Enter the details of activity
3. Enter the detail of department and save.