Project Management Re-Installation

Proposal Summary

This proposal covers the scope of Re-Installing the project module in Sandbox as per the implementation document provided by Magswitch.

Requirement

Magswitch wants to Re-install the project module in Sandbox based on the setup document of phase -1 implementation.

Our Solution

The project management module can be implemented in Sandbox based on the document provided.

Setup considerations are below

  • Define project templates and project records.
  • Set up project resources. This includes the generic resources, project Resource Roles and work calendars.
  • Set up project centers and roles.
  • Project Task Manager set up
  • Time Expense recording against project tasks
  • Project Tasks with work breakdown structure
  • Customized Planning and tracking view of project tasks under schedule tab
  • A custom subtab under related records tab to shoe purchase order and bills related to the particular project.
  • Custom saved searches
  • Project task form customization to include the “Milestone Invoiced” checkbox
  • Setup reminder portlet to include the saved search “Milestone Task To Be Invoiced”
  • Setting up project Dashboard
  • Setting a Baseline and operating with Gantt Chart

Risk

  • The custom solutions mentioned under the Customizations option in the “Magswitch_Prototype_Handover” document, user training, and Production Implementation are not included in this scope.
  • We will  re-implement only the solutions mentioned in the document in Sandbox and if any changes are required in the defined functionality/outcome have to be considered as a next scope after the preliminary implementation