Planned work center capacity on work orders

The amount of time being allocated to each work center per day will be shown in a Work Order once we enable the “Show Planned Capacity on Work Orders” preference.

Work orders will display a Planned Time subtab when we enable the preference.

This subtab will show each operation’s duration and associated work center.

To enable the preference;

Setup > Manufacturing > Manufacturing Preference

Under the Production execution section, check the “Show Planned Capacity on Work Orders” checkbox.

This will display a Planned Time subtab on work orders and automatically create planned time entries.