- NetSuite displays the start and end dates for a project in the time zone preference for the organization, selected in Company Information. For example, the company time zone is GMT -8:00 Pacific Time (US & Canada), and the project start date is 11/20/2022. Project staff in California and Japan will see the same start date, 11/20/2022 when viewing the project record.
- NetSuite displays the project task start and end dates based on the time zone preference of the user logged in. For example, a resource in New York is assigned to a project task with a start date of 10/28/2022 at 9:00 am. When an employee in California logs in and views the project, the start date for this task displays as 10/28/2022 at 6:00 am.
- For Fixed Start project tasks, the start time for the task is based on the time zone of the user who creates the task. If a user in New York creates a Fixed Start task with a start time of 9:00 am, the start time displays as 6:00 am to a resource viewing the task in California.
- No time zone conversion occurs for time entries. The planned time displays for a resource on the same date as the task date in the project schedule.